|
I.
II
|
Agreements:
Information pertaining to starting date of Centers, acceptance testing, Bill of materials at each location etc., are not maintained with respect to agreements entered to with Service Providers. The information available is not complete and it has been observed that proper records are not maintained.
Also no proper gate pass books are maintained for movement of material from each centre or from e-Seva.. Technical Support personnel deployment and their attendance records are not maintained.
A record of acceptance testing done at the time of start of the centre and afterwards it was claimed that periodical visits were done for verifying the working. No records are provided or available. Also additional counters are opened and equipment deployed. Proper records and dates were not available with the Technical Section. At least additional equipment deployed list should be available with the Technical Department or records have to be maintained. Also from GoAP funds any payments made on power, telephone, record of furniture-supplied records have to be maintained even if it is built on BOOT model. Even though Technical up keep is the responsibility of the partner if periodical checks are made, it should be reflected by way of records.
There are no SLAs in the agreements made. It is necessary to include in the new agreements made in future.
Checking transaction times taken etc., were not conducted. However, it is suggested to include transaction time taken as one of the parameters in the agreement.
Even though up-gradation of the technology is the responsibility of partners periodical checking and maintenance of records is a must as it is a BOOT agreement. Third Party Audit done and implementation carried out. Records to be maintained and periodically to be reviewed.
Even though the management and up-keep of the WAN is the responsibility of the Technology partners as the Leased lines and payment, demand note / payment all are carried out in the name of e-Seva, it is desirable and suggested to keep complete information on Leased lines, connectivity diagram centre-wise, district-wise and state-wide to be maintained along with the time validity. Complaint books maintained at the centers if reviewed periodically remedial actions and complaint redressal records to be maintained.
Observation - Rural e-Seva Centre at Bhongir
It has been observed that at Bhongir Rural e-Seva Centre the Technology partner has not installed the fire and smoke alarm detector system and kept it in packed condition only. It indicates that acceptance test is a must before starting the centres. Also gate passbook is not maintained and computer in the counter is not working. Information on such items has to be gathered and kept track of by maintaining records. The Bathroom facility is not maintained properly. The Technical Servers room is not maintained properly and wires are hanging loosely and no proper fixing has been done.
|
The information pertaining to starting date of centre, acceptance testing is in accordance with the agreement. Regarding the bill of material a each location inventory has been complete4d and a copy of the said reply has also been submitted to the Government.
e.Seva project is built on a PPP-BOO model. The project is started with 9 centers w.e.f. 25th Aug.2001. The telephone bills, connectivity charges and power bills for the project is met by the BOOT operator M/s.CMS Ltd.,. However government has paid for the manpower, furniture & interiors. The government expenditure is recorded property and dealt by the Administration Section of the e.Seva Project.
The new RFP envisages SLA for completing a transaction within 15 minutes. The SLA is being included in the new agreements as advised and the instructions will be noted for further guidelines.
The e.Seva software doesn’t have the facility to record the time stamp for each transaction. However in the present RFP bid document clear instructions/condit9ions imposed on the technology partners to specify time taken for each transaction. Further it is submitted that if the transactions penalties will be collected for such delay, which will also be, reflect in the software developed in the matter. By adopting this new technology, no intentional delay will be caused to the citizens and the service will also be improved. The time stamp is proposed to be captured for all transactions.
Regarding the up gradation of the technology although the responsibility lies with technology partners, necessary records will be maintained and periodical review will be done apart from periodic third party audits.
Further, in the new tender for Hyderabad the connectivity responsibility is with Government of AP and as suggested the complete information relating to the operational aspect of the project shall be maintained. Further, a grievance module shall be introduced for handled grievance.
The present staff is not sufficient to conduct acceptance test before stating of the e.Seva. Suitable action is being taken to maintain logbook and to improve the other items of work.
|
It can be mitigated by going for third party certification or by outsourcing the task to an agency selected through process. In future
e.Seva through identified empanelled agencies can go for acceptance check periodically. Permanent staff need not be thought of.
|